Panama City staff want $5.36 million in unspent Hurricane Michael FEMA money for new Downtown Marina slips. The City Commission takes it up Tuesday, Nov. 17.

Panama City staff want to spend about $5.36 million in unused Hurricane Michael recovery money on new boat slips at the Downtown Marina. The City Commission takes up the plan at 4 p.m. Tuesday, Nov. 17, at 840 W. 11th St.

The money is all that remains unassigned from the city’s FEMA funding for Hurricane Michael, according to a Nov. 6 memo from Public Works Director Clint W. Murphy to City Manager Jonathan H. Hayes. Staff recommend putting it toward the wet slips in the marina’s east basin, beside the boat ramp.

Where the money comes from

The $5,357,609.36 was set aside for two projects at the St. Andrews Marina, the memo says:

FEMA project Amount
St. Andrews Bulkheads (PW 1971) $772,940.00
St. Andrews Marina Infrastructure (PW 2295) $4,584,669.36
Total $5,357,609.36

Any money the city does not use must go back to FEMA, the memo says. That is why staff want a project expected to cost more than the amount available.

What it would build

The east basin plan covers new wet slips on Docks E, F, G and H. The memo gives these figures:

  • Original estimate: $6.5 million for the east basin slips.
  • Current estimate: $6 million. Staff say prices have come down and building all four docks under one contract avoids paying for several mobilizations.
  • The gap: anything above the FEMA money could come from the loan the commission has already approved for the Downtown Marina.

The slips are already designed by the engineering firm Turrell, Hall and Associates. The city has its permit from the U.S. Army Corps of Engineers and expects the Florida Department of Environmental Protection permit early in 2027, the memo says.

Why it could take a year

FEMA has to approve the swap first. It will check the project for environmental and historic preservation effects and review whether the scope meets its rules for an alternative project. Staff expect that process “could take a full year to complete.”

Staff say that timing fits the rest of the marina work. The memo says the west basin job, nearest Hotel Indigo, will take at least a year and up to 18 months once a contract is awarded. The east basin contractor would clear the T-Dock before the west basin contractor needs it. Staff also say the delay gives the St. Joe Company time to market the west basin slips before the east basin ones open.

The boat ramp is a separate vote

Commissioner Robbie Hughes asked for a second marina item on the same agenda: whether to put the downtown boat ramp out to bid. The agenda request for the boat ramp says the ramp and the docks around it are fully designed and permitted.

  • Estimated cost: $1.3 million, plus or minus 10%, for the whole job.
  • State grant: $300,000 from the Florida Fish and Wildlife Conservation Commission.
  • The rest: could come from the city’s Capital Improvement Revenue Refunding Note, Series 2025.

Staff have not made a recommendation on the ramp. The request asks the commission for direction.

What the commission decided Oct. 27

The ramp is on its own because the commission took it out of the slip contract last month. The Oct. 27 minutes, up for approval Tuesday, show the commission voted 5-0 to approve the revised scope for the west basin wet slips “minus the boat ramp.”

City Attorney Nevin Zimmerman said in the motion that the bidder itself must have the five years of marina construction experience. A bidder can add more experience through subcontractors on its team, the minutes say. Our story on the marina rebid has what the slip contract includes.

What it means for you

  • Nothing changes at the marina yet. Tuesday’s vote would only let staff ask FEMA to move the money. Construction in the east basin would not start until FEMA signs off.
  • Boaters: the ramp vote decides whether the city advertises that job now. A red tide caution from the health department has been in place at the marina boat ramp since Nov. 6.
  • Have your say: the commission takes public comment on agenda items before it votes, with three minutes per speaker. The full Nov. 17 agenda is on the city’s Agenda Center.

Frequently asked questions

What FEMA money is Panama City proposing to use at the Downtown Marina?

About $5.36 million in Hurricane Michael FEMA funding that the city has not yet assigned. It was tied to two St. Andrews Marina projects: bulkheads ($772,940) and marina infrastructure ($4,584,669.36).

What would the money build?

New wet slips on Docks E, F, G and H in the east basin of the Downtown Marina, next to the boat ramp. Staff estimate the work at $6 million.

When does the City Commission decide?

The item is on the agenda for the City Commission meeting at 4 p.m. Tuesday, Nov. 17, at 840 W. 11th St. If approved, FEMA must still review the project, which staff say could take a year.